Project Description
Becher Hoppe provided the construction services for
the Wadleigh Street Bridge over the Plover River in the
Village of Hatley. The
Plover River is a Class II trout stream making construction
more challenging to protect this habitat.
Project
Features
·
60’ long two-span flat
slab concrete bridge
·
Type M tubular steel
bridge railing
·
Steel piling foundations
·
Heavy riprap (using local
red granite)
·
Asphaltic pavement
approaches
·
Water and sewer
coordination with Village of Hatley
·
Pavement marking
Firm’s
Involvement
·
Agency coordination with
WDNR and Army Corp of Engineers
·
Utility coordination
·
Construction observation
and administration
·
Coordination with WisDOT
and Village of Hatley
|